Dam InflowsSummary

DAM AND INFLOWS SUMMARY – WEDNESDAY, 6 JANUARY 2021

Dam Operating Percentage % full Volume (m3)
Insiza Mayfair Y 44.93 77,953,697
Inyankuni Y 41.89 33,835,750
Lower Ncema Y 21.08 3,844,660
Umzingwane Y 18.97 8,470,900
Upper Ncema Y 28.17 12,806,900
Mtshabezi Y 30.28 15,744,400
Totals Operational Dams 36.82 152,656,307

Cumulative Dam Inflows to date as at Wednesday, 6 January 2021.

Dam Cumulative % Cumulative Actual Inflows 5.1.2021 Inflows 6.1.2021
Insiza 21.05 36,525,221.40 0 0
Inyankuni 2.85 2,298,370.00 0 0
L/Ncema 13.54 2,468,810.00 0 0
Umzingwane 12.67 5,659,860.00 0 0
U/Ncema 22.79 10,489,900.00 0 0
Mtshabezi 7.76 4,033,00.00 0 0
Total 14.82 61,431,361.40 0 0

The three supply Dams previously decommissioned have been recommissioned.

However, water supply to residents is still constrained.

The New Flowserve pumps which are replacing the obsolete KSB Pumps have been installed at Ncema and Fernhill Pump Stations and are still undergoing the technical commissioning. Council is working flat out with the Contractor to ensure that pumps are fully operational as soon as possible.

The Water shedding schedule will be reviewed at the end of January 2021.

Advert Number:

C DUBE TOWN CLERK

Date: Wednesday, 6 January 2021